(03 June 2013 - 08 June 2013)

Monday 03 June 2013: Laundry/Ensuite Tiled 

Today the Laundry wall was tiled and grouted. And also the Ensuite wall tiles were grouted. The grout is the same as the tile colour. 

Laundry Tiles
Laundry
Ensuite
Ensuite Shower
Ensuite Tub

Tuesday 04 June 2013: Powder/Main Bathroom Tiled 

Tiling to the wet areas are complete now. Bathrooms are looking good. Our neutral floors and walls look nice. 

The site supervisor called in today to give us the weekly update but still unable to tell us when we will receive the keys.

Powder Room
Main Bathroom
Wednesday 05 June 2013: Balcony/Alfresco Tiles 

The tilers completed the Balcony and Alfresco tiles today. We kept the same tiles to both.
Now that the tiling is completed, I think the next stage is painting. I am happy with the result and our choices.

Balcony
Alfresco