Wednesday, January 23, 2013

Week 04 - Ground Floor Frames

(14 Jan - 19 Jan 2013)

Monday 14 January 2013: Ground Floor frames partially completed


Our first level frames were delivered today so we are pretty happy about that. We are also pretty stoked as we have weather forecast so hopefully this helps get things done. The Ground floor frames were partially completed.

Study and Rumpus Room

Wednesday 16 January 2013: Ground floor fully completed

With the frames they deliver the Ground floor and when it's finished they then deliver the first floor and the truck puts it straight up on top of the first storey. We noticed today that top level frames have been delivered. It's starting to take shape. Compared to yesterday only a little work appears to have been done today. The beams were put in place for the first storey, the wood has been moved up there too, ready to be put together next week. The Ground first floor has had a few boards put up around the internal & external walls.

I can't wait to get up to the block on the weekend and have a look around, it's going to be so exciting to finally walk around in our new house. Now, it's just a matter of days till I receive the next invoice, then I can say it's officially done.
Kitchen Window
Ladder to First floor